CONTRACTORS replacing a bridge linking docks between Birkenhead and Wallasey plan to start work on floating the new structure into position this weekend.

The project on Tower Road in Birkenhead began last March and has been delayed by "unforeseen obstructions".

It has caused tailbacks and frustration for rush hour motorists, who have had to find alternative routes.

Wirral Council and Dawnus Construction confirmed today that the dock passage from nearby Peel Ports will be closed for a week from this Saturday, in order to complete the next stage of work.

If all goes to plan next week, it is hoped the road will fully reopen to motorists on Monday, March 26.

The aim is to move the new bridge – ready and awaiting transport by barge and truck from the contractor's yard on the quay side – into position between Alfred Dock and East Float.

But, for safety reasons this can only go ahead if the weather and tidal conditions allow.

The barge required to move the bridge is currently waiting for clearance to leave port in Holland and can only operate the bridge installation process if wind speeds remain below 12mph.

As with any major project, this date remains provisional subject to weather conditions and technical processes, but once the bridge is in position, the contractors and the Council are confident that a significant milestone will have been reached.

Kevin Lucas, Director North West at Dawnus Construction, said: "Of the two bridges we are replacing on this scheme, the replacement lift bridge has been a true engineering challenge.

"Many technical issues have been addressed. Unforeseen ground conditions and the numerous historical dock features encountered behind the dock wall have added time to the programme.

"But we are nearly there.

"We apologise for any disruption the programme overrun may have caused and thank local residents and road users for their patience.

"We can assure you that everything in our power is being done to get Tower Road re-opened to traffic as soon as practically and safely possible."

Cllr Stuart Whittingham, cabinet member for highways and transport, added: "Our staff are continuing to work closely with the contractor and Peel Ports to schedule the critical activities involved in floating the new bridge into place, which will allow them to then carry out the essential testing and commissioning required for the bridge to operate correctly and safely so it can be opened to traffic.

"I am disappointed that the contractor is still unable to provide us with definite dates for the bridge installation and road re-opening.

"However, this project is incredibly complex and though we hope the bridge can be floated in next week there are considerable risks that remain out of our control.

"We know that people who use this route on a regular basis have been considerably inconvenienced and frustrated by the length of time this project has taken and the additional delays the project has been subject to.

"As always, I can only show my appreciation for their continued patience."