THE M53 motorway will be closed this weekend due to a 26-metre-long hydrogen furnace being delivered to Essar Oil UK’s Stanlow refinery near Ellesmere Port in Cheshire.  

After arriving by ship from Thailand to the Port of Liverpool in June it was transferred to a barge for the short trip across the River Mersey, through the locks into the Manchester Ship Canal and onto a holding bay near National Waterways Museum at Ellesmere Port.

The last leg of its 6,000 mile and mostly watery journey will be along the M53 motorway and A5117 local road.

Gordon Beattie, abnormal loads manager for the North West said: “There are abnormal loads and there are abnormal loads and this one will completely fill the motorway.

“The module will be mounted on two wheeled platforms, one on each carriageway, and will look a bit like the bridge of a container ship gliding down the motorway.

Wirral Globe: The module has already been moved across the River Mersey and up the Manchester Ship Canal to a landing site next to the M53 in readiness for next week's three-mile move by road to Stanlow.(Image: National Highways)The module has already been moved across the River Mersey and up the Manchester Ship Canal to a landing site next to the M53 in readiness for next week's three-mile move by road to Stanlow.(Image: National Highways)

“This has been a huge logistical challenge for everyone involved but we’ll be closing the motorway at a time when traffic is at its lightest and a very good diversion will be in place.”

On Saturday, August 13, the furnace will be moved away from the canal a few hundred yards onto the neighbouring M53 via the southbound entry slip road at junction 8.

Straddling both the northbound and southbound carriageways the module will then be slowly and carefully moved at a walking pace three miles onto Essar Oil UK’s Stanlow site, exiting the M53 at junction 10 and travelling along the A5117 local road.

The largest single ‘module’ for the new furnace is 26.5 metres long, 18.5 metres tall, and 14.2 metres wide.

The refinery is located on the south bank of the River Mersey, flanked on its west by the M53 and M56 to the south.

Wirral Globe: The module has already been moved across the River Mersey and up the Manchester Ship Canal to a landing site next to the M53 in readiness for next week's three-mile move by road to Stanlow.(Image: National Highways)The module has already been moved across the River Mersey and up the Manchester Ship Canal to a landing site next to the M53 in readiness for next week's three-mile move by road to Stanlow.(Image: National Highways)

The southbound carriageway will be closed between junction 5 at Hooton and junction 10 for Cheshire Oaks from 7pm on Saturday, August 13 until 10am on Sunday, August 14.

The northbound carriageway will be closed between junction 10 and junction 8 with the closure time on Saturday evening after 7pm and subject to an appropriate reduction in traffic levels from Cheshire Oaks.

A diversion using the A550 and A494 trunks will operate between junction 5 and junction 11 at Stoak Interchange where the M53 meets the M56

The new furnace is part of Government-backed plans to include hydrogen in the race to reduce the country’s carbon emissions to net zero by 2050.

Stewart Prentice, Head of Projects, at Essar said: “We would like to thank National Highways for their support in this mammoth task, especially in facilitating closure of the M53 as our new furnace travels on its final leg to Stanlow.

"The new furnace is one of the largest objects ever to be moved on UK roads and key to Essar’s strategy of transitioning to being a low carbon energy provider at the forefront of decarbonisation in the North West.”